October 2026 Update
Prithvi
Tower H3 Gallery

ElevationElevation
Work in Progress

Indoor PhotosH3A bathroom dado & flooring work
Completed till 2nd floor.

Indoor PhotosH3A bathroom dado & flooring work
Completed till 2nd floor

Indoor PhotosH3 A bathroom plumbing line consealed work
Completed till 4th floor

Indoor PhotosH3 A bedroom flooring wprk
Completed till 2nd floor

Indoor PhotosH3 A internal flooring tile work
Completed till 2nd floor

Indoor PhotosH3 A Internal gypsum plaster work
Completed till 3rd floor

Indoor PhotosH3 A internal walls work
Completed till 7th floor