November 2026 Update

Parc Residences

Tower A1 A Gallery

Building A1
ElevationBuilding A1

RCC completed

Flooring work
Indoor PhotosFlooring work

Completed

Lift installation
Indoor PhotosLift installation

Completed

Internal plaster work
Indoor PhotosInternal plaster work

100% completed

Terrace work
Indoor PhotosTerrace work

Completed

Window installation
Indoor PhotosWindow installation

Completed

CP fitting work
Indoor PhotosCP fitting work

Completed.

Directory board
Indoor PhotosDirectory board

Installed

Call